Abu Dhabi Distribution Company - ADDC -
Water Supply
1. Preparation & Submission of Demand Calculations
2. Approval for Water Demand Calculations by ADM - Construction NOC
3. Preparation & Submission of Water Supply Drawings
4. Approval for Water Supply Drawings by ADDC - Construction NOC
Abu Dhabi Civil Defense - ADCD
2. Approval of Fire Alarm & Emergency Light Drawings
3. Preparation & Submission of Fire Fighting Drawings
4. Approval for Fire Fighting Drawings by ADCD - Construction NOC
5. Preparation & Submission of Gas System Drawings
6. Approval for Gas System Drawings by ADCD -
Construction NOC
Etisalat
2. Approval for Shop Drawings by Etisalat - Construction NOC
District Cooling
(Between District Cooling Provider & Contractor)
1. Preparation & Submission of ETS Room Shop Drawing Drawings
2. Approval for ETS Room Shop Drawings - Construction NOC
2. Approval for ETS Room Shop Drawings - Construction NOC
Abu Dhabi Sewerage
Company - ADSSC & Public Garden Directorate (PGD) - Storm Water
1.Preparation & Submission of Drainage Shop Drawings
2. Approval for Drainage Shop Drawings by ADSSC - Construction NOC
3. Preparation & Submission of Storm Water Shop Drawings
4. Approval for Storm Water Shop Drawings by PGD - Construction NOC
2. Approval for Drainage Shop Drawings by ADSSC - Construction NOC
3. Preparation & Submission of Storm Water Shop Drawings
4. Approval for Storm Water Shop Drawings by PGD - Construction NOC