Construction
Project Documentation and Database Management
In order to properly manage any construction project documents are very important such as design documents, contracts, submittals, contract claims and credit documents, logs, and schedules etc. Based upon the instructions from the client, the architect prepares sketches and/or drawings to present to the appropriate consultants for his or her review and implementation into the design process. Each consultant is a licensed professional in his or her respective field. The structural engineer is responsible for the design of the floor framing systems, their supports, and foundations. The mechanical engineer is responsible for the heating and ventilation systems, electrical and plumbing requirements, and life-safety systems. High-rise office buildings may require an elevator consultant whose expertise is programming the number and time duration for people movement and related equipment. The civil engineer, also known as the site engineer, is responsible for the site grading and drainage,access roads, and parking requirements. On certain projects there may be additional specialized consultants, such as geotechnical, acoustical, window/façade, elevator, laboratory, landscaping, and blast engineering to assist the architect for the particular needs of the project
The importance of documents at construction site as follows-
1) It is required by law
2) It is required by the terms of the contract
3) It is needed to control the on-going work
4) It is neeeded as data for estimating future work
5) It is needed for preserving the contractor's rights under the contract
A good set of records that might be kept on a fair sized construction project could well include the
following files. Note that these files are assembled into blocks of like subject matter. This approach
greatly facilitates ease of filing and subsequent recall.
1) Original Contract Tender Documents
2) Issued for Construction set, and all subsequent revisions
3) Instructions to contractor
4) Contemplated Change Notices issued by the owner, Change Estimates, and Change Orders
received
5) Sub-contractor quotes, contracts, purchase orders and correspondence
6) Shop drawings, originals, all revisions and re-submissions
7) Shop drawing transmittals, and transmittals log
8) Daily time records
9) Daily equipment use
10) Daily production logs, e.g. concrete pours etc.
11) Material Delivery and Use Records, including expediting
12) Accounting records: pay-roll, accounts payable and receivable, etc.
13) Progress Payment Billings under the contract
14) Daily Force Account Records, pricing and billings
15) Contract Milestone Schedule or Master Schedule
16) Short Term Schedules and up-dates
17) Task schedules and analyses
18) Original tender estimate
19) Construction control budget
20) Actual Cost Reports, weekly or monthly, including Exception Reports.
21) Forecast-to-Complete Estimate up-dates
22) Productivity Reports/Analyses
23) Inter-office correspondence, including memos and faxes (all filed by topic).
24) Contract correspondence
25) Minutes of Contractual Meetings
26) Minutes of Site Coordination Meetings
27) Requests for information
28) Notice of claims for delays and/or extra cost by contractor
29) Government Inspection Reports
30) Consultant Inspection Reports
31) Accident Reports
32) Daily diary or journal entries
33) Notes of telephone conversations
34) Progress Reports, weekly, monthly or quarterly
35) Progress photographs
36) Any other reports, such as special consultant reports
37) A Filing Record of all the Record Files that are being maintained
following files. Note that these files are assembled into blocks of like subject matter. This approach
greatly facilitates ease of filing and subsequent recall.
1) Original Contract Tender Documents
2) Issued for Construction set, and all subsequent revisions
3) Instructions to contractor
4) Contemplated Change Notices issued by the owner, Change Estimates, and Change Orders
received
5) Sub-contractor quotes, contracts, purchase orders and correspondence
6) Shop drawings, originals, all revisions and re-submissions
7) Shop drawing transmittals, and transmittals log
8) Daily time records
9) Daily equipment use
10) Daily production logs, e.g. concrete pours etc.
11) Material Delivery and Use Records, including expediting
12) Accounting records: pay-roll, accounts payable and receivable, etc.
13) Progress Payment Billings under the contract
14) Daily Force Account Records, pricing and billings
15) Contract Milestone Schedule or Master Schedule
16) Short Term Schedules and up-dates
17) Task schedules and analyses
18) Original tender estimate
19) Construction control budget
20) Actual Cost Reports, weekly or monthly, including Exception Reports.
21) Forecast-to-Complete Estimate up-dates
22) Productivity Reports/Analyses
23) Inter-office correspondence, including memos and faxes (all filed by topic).
24) Contract correspondence
25) Minutes of Contractual Meetings
26) Minutes of Site Coordination Meetings
27) Requests for information
28) Notice of claims for delays and/or extra cost by contractor
29) Government Inspection Reports
30) Consultant Inspection Reports
31) Accident Reports
32) Daily diary or journal entries
33) Notes of telephone conversations
34) Progress Reports, weekly, monthly or quarterly
35) Progress photographs
36) Any other reports, such as special consultant reports
37) A Filing Record of all the Record Files that are being maintained
Nice content thanks for sharing .. BIM Consulting in USA
ReplyDeleteBIM documentation in USA
BIM Implementation in USA