Pipeline and Technical Service Division, Abu Dhabi Gas Industries
Ltd. - (GASCO) NOC- Gas connections
Abu Dhabi Police NOC- Fire information and response emergency time
Abu Dhabi Distribution Company Asset Dep. (ADDC) - Water NOC- Potable
water and fire fighting
Abu Dhabi Distribution Company Asset Dep. (ADDC) - Electricity NOC-
Electricity
Abu Dhabi Transmission & Dispatch Company (TRANSCO) NOC- High
voltage electricity requirements
Abu Dhabi Sewerage Services Company (ADSSC) NOC- Sewerage
Relevant Municipal - Parks and Recreation Facility Divisions NOC-
Irrigation
Etisalat NOC- Telecommunications
Abu Dhabi Civil Defence NOC- Fire hydrant network; building fire and
life safety
UAE General Civil Aviation Authority (GCAA) NOC- Building height related
issues
Volume 3 - Operations Relevant Municipality - Health and Safety
Department Construction health and safety approval
Volume 2 - Design Relevant Municipality - Building Permit Department
Building permit issued
Volume 3 - Operations
Appendix 1 - Estidama
Relevant Municipality - Health and Safety Department Construction health
and safety
Volume 3 - Operations
Awqaf-appointed maintenance company Compliance with operations and
maintenance standards (For Mosque projects)
Appendix 1 - Estidama guidelines
Submit preliminary design
Site Enabling Works
Ongoing operation and maintenance of mosque
Construction of mosque-Full and final submission of architectural and
structural designs for building permit
Initial
Stage Requirement in Detail
Client/Engineer
1.
Receive Existing Fencing Permit by the
Engineer
2.
Issue Official Arabic Letter To ADM for
Appointing Contractor
3.
Receive Affection Plan by the Engineer
4.
Receive Exists As built Drawings For U.G.
Utilities
5.
Revise and Approve HSE Plan by Engineer
6.
Apply to Get on IFC Drawings
7.
Issue IFC Drawings
Design NOC’S by the Engineer
1.
From ADCD FOR Lights Drawings , Fire
Fighting, LPG, Passive Protection & Fire Strategy
2.
Design NOC From ADSSC
3.
Design NOC From Etisalat
4.
Design NOC
from ADDC
5.
Design NOC From Survey Department
6.
Design NOC From PRFD
7.
Design NOC From ADM
8.
Design NOC for Obstruction Lights and
Aircraft Warning Light by ADCA
Required authority approval
to start the work -Abu Dhabi Muncipality(ADM)
1.
Verify the Key site Demarcation Points by the
Engineer &ADM
2.
Establish Key Points on Site for Demarcation
3.
Obtain Building Permit from ADM
4.
Plot Initial Demarcation By ADM
5.
Update Existing Fencing Permit &Obtain
NOC for Sign Boards
6.
Hand over All Piles works to ADM After
Integrity Tests By Piling Subcontractor
7.
Revise and Approve HSE Plan by ADM
8.
Issuance of Drainage Design NOC
9.
Issuance of Storm Water Design NOC
10. Issuance
of Irrigation Design NOC
11. Issuance
of Water Supply Design NOC
Abu Dhabi Distribution Company - ADDC - Electrical (HV)
1.Issuance of
Substation Layout
2.Issuance of
Load Demand Notification (LDN) (Drawings & Calculations Approvals)
District
Cooling
1.Issuance of
Design information for District Cooling
Through The Engineer
Approvals Required
During Execution of the Project
Abu Dhabi Distribution Company - ADDC - Electrical (HV)
1.Preparation &
Submission of Substation Detailed Coordination Drawings Layout by Contractor 2Approval of Substation Detail Coordination Drawings Layout by ADDC
3. Preparation & Submission of Transformer Material
4. Approval for Transformer Material by ADDC
5. Preparation & Submission of HV Panel Material
6. Deliver of Materials
7. Approval for HV Panel Material by ADDC
3. Preparation & Submission of Transformer Material
4. Approval for Transformer Material by ADDC
5. Preparation & Submission of HV Panel Material
6. Deliver of Materials
7. Approval for HV Panel Material by ADDC
Abu Dhabi
Distribution Company - ADDC - Electrical (LV)
1. Submission of Bus bar Material
2. Approval for Bus bar Material by ADDC
3. Preparation & Submission of Switchgear Material
(LV Panel & Capacitor Bank)
4. Approval for Switch gear Material (LV Panel &
Capacitor Bank) by ADDC
5. Preparation & Submission of ATS Panels (Automatic
Transfer Switch Panels) Material 6.Approval for ATS Panels
(Automatic Transfer Switch Panels) Material by ADDC
7. Preparation & Submission of Power Cables Material
8. Approval for Power Cables Material by ADDC
9. Preparation
& Submission of Generators Material
10. Deliver of Materials
11. Approval for Generators
Material by ADDC
Thanks for the information Mr. Azeez. Appreciate your effort to spread the knowledge and awareness.
ReplyDeleteThank you Abdul Azeez brother for sharing such a useful information with us.
ReplyDeleteRegards!
Ashfaq Ahmad