NOC requirements for building permit- Abu Dhabi


Pipeline and Technical Service Division, Abu Dhabi Gas Industries
Ltd. - (GASCO) NOC- Gas connections
Abu Dhabi Police NOC- Fire information and response emergency time
Abu Dhabi Distribution Company Asset Dep. (ADDC) - Water NOC- Potable water and fire fighting
Abu Dhabi Distribution Company Asset Dep. (ADDC) - Electricity NOC- Electricity
Abu Dhabi Transmission & Dispatch Company (TRANSCO) NOC- High voltage electricity requirements
Abu Dhabi Sewerage Services Company (ADSSC) NOC- Sewerage
Relevant Municipal - Parks and Recreation Facility Divisions NOC- Irrigation
Etisalat NOC- Telecommunications
Abu Dhabi Civil Defence NOC- Fire hydrant network; building fire and life safety
UAE General Civil Aviation Authority (GCAA) NOC- Building height related issues
Volume 3 - Operations Relevant Municipality - Health and Safety Department Construction health and safety approval
Volume 2 - Design Relevant Municipality - Building Permit Department Building permit issued
Volume 3 - Operations
Appendix 1 - Estidama
Relevant Municipality - Health and Safety Department Construction health and safety
Volume 3 - Operations
Awqaf-appointed maintenance company Compliance with operations and maintenance standards (For Mosque projects)
Appendix 1 - Estidama guidelines
Submit preliminary design
Site Enabling Works
Ongoing operation and maintenance of mosque
Construction of mosque-Full and final submission of architectural and structural designs for building permit


 Initial Stage Requirement in Detail

Client/Engineer

1.    Receive Existing Fencing Permit by the Engineer
2.    Issue Official Arabic Letter To ADM for Appointing Contractor
3.    Receive Affection Plan by the Engineer
4.    Receive Exists As built Drawings For U.G. Utilities
5.    Revise and Approve HSE Plan by Engineer
6.    Apply to Get on IFC Drawings
7.    Issue IFC Drawings

Design NOC’S by the Engineer

1.    From ADCD FOR Lights Drawings , Fire Fighting, LPG, Passive Protection & Fire Strategy
2.    Design NOC From ADSSC
3.    Design NOC From Etisalat
4.    Design NOC  from ADDC
5.    Design NOC From Survey Department
6.    Design NOC From PRFD
7.    Design NOC From ADM
8.    Design NOC for Obstruction Lights and Aircraft Warning Light by ADCA

Required authority approval to start the work -Abu Dhabi Muncipality(ADM)

1.    Verify the Key site Demarcation Points by the Engineer &ADM
2.    Establish Key Points on Site for Demarcation
3.    Obtain Building Permit from ADM
4.    Plot Initial Demarcation By ADM
5.    Update Existing Fencing Permit &Obtain NOC for Sign Boards
6.    Hand over All Piles works to ADM After Integrity Tests By Piling Subcontractor
7.    Revise and Approve HSE Plan by ADM
8.    Issuance of Drainage Design NOC
9.    Issuance of Storm Water Design NOC
10. Issuance of Irrigation Design NOC
11. Issuance of Water Supply Design NOC

    Abu Dhabi Distribution Company - ADDC - Electrical (HV)                 

  1.Issuance of Substation Layout                
  2.Issuance of Load Demand Notification (LDN) (Drawings & Calculations Approvals)
       District Cooling                   
 1.Issuance of Design information for District Cooling  Through The Engineer            

Approvals Required During Execution of the Project
Abu Dhabi Distribution Company - ADDC - Electrical (HV)                                                           1.Preparation & Submission of Substation Detailed Coordination Drawings Layout by Contractor   2Approval of Substation Detail Coordination Drawings Layout by ADDC
3. Preparation & Submission of Transformer Material
4. Approval for Transformer Material by ADDC
5. Preparation & Submission of HV Panel Material
6. Deliver of Materials
7. Approval for HV Panel Material by ADDC
Abu Dhabi Distribution Company - ADDC - Electrical (LV)            
1. Submission of Bus bar Material                
2. Approval for Bus bar Material by ADDC              
3. Preparation & Submission of Switchgear Material (LV Panel & Capacitor Bank)                    
4. Approval for Switch gear Material (LV Panel & Capacitor Bank) by ADDC                 
5. Preparation & Submission of ATS Panels (Automatic Transfer Switch Panels) Material         6.Approval for ATS Panels (Automatic Transfer Switch Panels) Material by ADDC                     
7. Preparation & Submission of Power Cables Material                  
8. Approval for Power Cables Material by ADDC                
9. Preparation & Submission of Generators Material                         
10. Deliver of Materials                   
11. Approval for Generators Material by ADDC     

2 comments:

  1. Thanks for the information Mr. Azeez. Appreciate your effort to spread the knowledge and awareness.

    ReplyDelete
  2. Thank you Abdul Azeez brother for sharing such a useful information with us.
    Regards!
    Ashfaq Ahmad

    ReplyDelete